Hello Micronet,

Does anyone out there have any experience with MS Project 2003. I have a
procedure question. Let's say I have a series of project tasks with
originally projected FINISH dates. Suppose they aren't met. How do I keep
the original finish date in the project and then add a new finish date? This
seems like it ought to be a no-brainer, but I can't figure out what column
to use to indicate the new finish date.

Happy New Year! Hopefully the project will be complete before the next one .
. .

Thanks,

Bond
-=-=-=-
E. Bond Francisco
510-643-5523
Computer Resource Manager
CMMS Administrator
Physical Plant - Campus Services
UC Berkeley

------------------------------------------------------------------------
The following was automatically added to this message by the list server:

For information about Micronet, including subscribing to
or unsubscribing from its mailing list and finding out
about upcoming meetings, please visit the Micronet Web site:
<http://micronet.berkeley.edu/>.
Received on Mon Jan 3 09:46:47 2005

This archive was generated by hypermail 2.1.8 : Mon Jan 03 2005 - 09:47:00 PST